Identifying difficulties, promptly removing obstacles and preparing necessary conditions to speed up the construction progress are urgent tasks for the first months of the year and the whole year of 2023.
Identifying difficulties and problems
According to the Department of Planning and Investment of Yen Bai province, in the period 2021-2025, Yen Bai province will implement 26 key projects, with a total investment of over 12,740 billion VND; in which, 5 projects forwarded, 21 new projects started. Mainly focusing on projects in the field of transportation, accounting for 17 projects with a total investment of over 9,000 billion VND.
Currently, the whole province is trying to implement 16 projects, by the end of 2022, nearly 4,000 billion VND of medium-term capital has been allocated and disbursed; in which, the completed volume of transition projects reaches 90%, new construction projects reach from 20% to 45%. Compared with the proposed plan, so far, the implementation progress of key projects has been slow and has not met the requirements, affecting the disbursement of the province.
According to Mr. Tran Huy Tuan, Chairman of the People’s Committee of Yen Bai province, in the past time, due to the complicated situation of the COVID-19 epidemic; Due to the high prices of materials and raw materials, adverse weather conditions, etc., the construction process faced many difficulties, especially projects in the field of transportation, many projects increased capital, leading to it takes time to carry out the procedures to adjust the total investment.
The delay is also due to the lengthy preparation work of some projects, especially these projects have large scale, high requirements on architecture, need to organize the selection of consultants and architectural examinations, so it takes a lot of time. time, such as: Yen Bai Provincial Convention Center; Headquarters of the Provincial Party Committee and Party Committees; The headquarters of the Radio and Television Station of Yen Bai province…
The work of site clearance is also difficult because the compensation level is still low compared to the market price, in some special cases there is no support policy, compensation when implementing land recovery, the application of support policies. Support is not really flexible, still rigid. Most of the key traffic projects face this difficulty, typically the road project connecting national highway 37, national highway 32C with Noi Bai – Lao Cai highway; the road connecting national highway 32 with provincial road 174; Project to repair and upgrade Tram Tau – Bac Yen route (Son La)…
In addition, some projects carried out the work of acceptance, handover, completion of documents, payment procedures, project finalization, which were slow, still made mistakes compared to regulations, took a long time to edit and complete documents. profile; In particular, the organization selected incompetent contractors, construction was behind schedule compared to requirements, often violated the time of making the final settlement report.
Mr. Nguyen Quoc Thinh, Director of Yen Bai Traffic Construction Joint Stock Company, said that most construction roads in Yen Bai province have steep slopes, rugged terrain and are far from the source of raw materials. The volume of earthworks is large and it is very difficult to move construction machinery and equipment…
Moreover, the specificity of Yen Bai province is that annual rainfall is usually higher than the national average, the guarantee period for construction is only from 3 months to 5 months per year. Many items and roads are regularly threatened by flash floods and landslides when the rainy season comes. These are huge disadvantages, reducing construction progress and causing damage to traffic contractors.
Remove difficulties and speed up progress
The resettlement area under the integrated development subproject of dynamic urban centers in Yen Bai city has been delayed by 2 months, while the completed volume is estimated at 60% of the plan.
In order to speed up the progress of key works and projects, Yen Bai province has directed the investor units to closely coordinate with localities to periodically check, carefully review and develop detailed scenarios to solve problems. The budget is suitable to the construction schedule for each project or work, ensuring the quick completion of each item and the quality of the work as planned.
Mr. Nguyen The Phuoc, Vice Chairman of Yen Bai Provincial People’s Committee, said that the province has set up a working group to follow each project, promptly remove obstacles, promote capital disbursement through correct and sufficient payment. completed quantity. At the same time, it is required to tighten discipline and discipline, promote the sense of responsibility, strictly handle cases where investors and contractors violate the reporting time; do not leave a backlog in the work of acceptance, handover, completion of documents, procedures for payment and settlement of projects according to regulations.
Along with that, Yen Bai province promptly proposed a number of practical solutions, specifically: improving the quality of investment preparation for projects through quickly inviting qualified consultants. quality, have deep professional capacity; regularly review sources of revenue increase and cost savings in order to timely allocate to projects capable of absorbing capital; strengthen propaganda, advocacy and dissemination of land policies and laws, flexibly apply policies to support site clearance; assign specific coordination responsibilities to each investor with relevant agencies.
Local authorities are responsible for site clearance, the investor follows the direction of tidying up each part, appraising, approving, and paying the cost to go there. immediately carry out construction there, giving priority to site clearance for construction and resettlement to serve investment projects.
The investor strengthens inspection, supervision, and urges contractors to speed up the construction progress, ensuring compliance with commitments with the investor; resolutely handle in accordance with law against contractors who violate the signed contract terms; adjust, replace contractors or supplement subcontractors for contractors who do not meet the required capacity.
Regarding capital rotation, according to Mr. Doan Huu Phung, Director of the Department of Planning and Investment of Yen Bai province, in addition to allocating and ensuring capital early in the year, Yen Bai province will flexibly adjust the capital plan. according to the principle of adjusting capital reduction of completed projects, out of spending tasks, and facing difficulties or obstacles with slow implementation progress to supplement capital for projects with completed volume but still lacking capital. , it is necessary to speed up the implementation progress and projects lacking capital for site clearance.
For projects about to start construction, Yen Bai province requires the investor units to urgently complete the selection of survey consultants, prepare feasibility study reports, prepare, appraise and approve. projects in the second and third quarters of 2023, ensuring the commencement of the remaining 10 projects in 2023 and 2024.